We’re installing high-capacity underground pipework across Enfield to form a heating super-highway. In the future branches will be added to supply residents across Enfield with heating and hot water from Energetik’s near zero carbon energy centre at the Edmonton Eco- Park. This will help decarbonize heating and hot water in tens of thousands of homes in the borough, as part of Enfield’s wider net-zero ambitions. In order to achieve this, we will install pipework in the ground that we expect will never have to be revisited until the end of its useful life at the turn of the next century.

How will the works be delivered?

Whilst we appreciate that any road disruption can cause inconvenience, we have designed the route to minimise disruption, including maintaining existing bus routes, adequate access for all local residents, and for the majority of the route, we will maintain a two way traffic flow as normal. The works will be delivered in short 50m-100m sections, which will result in some parking bays being suspended as the works move along Hertford Road. The work areas will be segregated by suitable fencing to ensure a safe working area for the work force and provide a safe route for the public at all times.

We have notified the local community living in the immediate area by way of letter to all properties along the length of the streets affected and into adjoining streets. For those outside of this local delivery area, the advanced warning notices, have been put up to advise those passing through. For information on each section, please see more information below, and on the Enfield Council’s website: https://www.enfield.gov.uk/services/roads-and-transport/road-works.

  • Current works: Houndsfield Road/Hertford Road N9

    Location/Area: Houndsfield Road/Hertford Road N9

    Estimated start date: 2nd January 2024

    Estimated end date:  16th February 2024

    Reason:  Heat Network Extension

    Working hours:  08:00 – 17:30, Saturday 08:00 – 13:00 and Sunday 09:00 – 13:00 (non-noisy works)

    For more information, consult the Enfield Council’s dedicated page: Road closures 

     

     

    A 70-meter section of works on Hertford Road between 259 and 277 to enable district heating pipe installation will be taking place on the above dates.

    So that works can be undertaken safely, the cycle lane and parking bays on the west side of Hertford Road N9 will be suspended and the works area will be enclosed with barriers.

    The diversion route for access will be Via Cleveland Road and Doncaster Road. Two Way Traffic will be maintained on Hertford Road N9.

    How may this work affect you?

    Access and Parking:

    Access will always be maintained for residents. In the event you might need assistance, please ask a member of our staff by contacting us with the numbers provided below.

    The work areas will be segregated by suitable fencing to ensure safe working area for the work force and provide safe route for public at all times.

    A temporary diversion route will be in place.

    Useful Contact details

    Emergency / Out of Hours Contacts:

    Project Manager:           Tony Doona 07960 547 252

  • Current works: Angel Walk

    Location/Area: Angel Walk

    Estimated start date: 13th January 2024

    Reason:  Heat Network Extension

    Working hours: Monday to Friday 08:00 – 17:30 and Saturday 08:00 – 13:00

    For more information, consult the Enfield Council’s dedicated page: Road closures 

    Following the completed works on Cemetery Walk, the next portion of pipework will be installed mainly in the footpath along Angel Walk from Montagu Road to Angel Gardens. There will be a temporary cycle lane suspension over the duration of works as well as access for construction vehicles that will be facilitated via an emergency access gate between Rays Road and Angel Gardens.

    How may this work affect you?

    Access and Parking:

    Pedestrian and vehicle access will always be maintained for Rays Rd. In the event you might need assistance, please ask a member of our staff by contacting us with the numbers provided below.

    There will be 2 parking bays being suspended adjacent to Angel Gardens emergency gate to facilitate access and egress for construction vehicles.

    The work areas will be segregated by suitable fencing to ensure safe working area for the work force and provide safe route for public.

    Pedestrians will have access to an alternative route, as a shared path for cyclists and pedestrians will be available throughout the duration of these works.

    Useful Contact details

    Emergency / Out of Hours Contacts:

    Site Manager:                Andrew Heffernan – 07384 298 392

    Project Manager:          Dan Pintea – 07478 833 389

    Contracts Manager:     Hakan Balcioglu – 07306 502 902

  • Current works: Advent Way

    Location/Area: Advent Way

    Estimated start date: 17th January 2024

    Estimated end date:  18th January 2024

    Reason:  Crane operation to lift pipe bridge for Heat Network Extension

    Working hours: 22:00 – 06:00

    For more information, consult the Enfield Council’s dedicated page: Road closures 

    There will be a full road closure in place along Advent Way overnight to enable safe mobile crane operation whilst positioning the pipe bridge crossing the Pymmes Brook. The area affected is shown below. The estimated start date will be finalised nearer the time based on the weather forecast and will be updated accordingly.

    A diversion will be in operation from 22:00 to 06:00 with diversion signs in place for the duration of the closure.

    Location/Area: Advent Way

    Estimated start date: 18th January 2024

    Estimated end date:  29th March 2024

    Reason:  Installation and connection of pipe for Heat Network Extension

    Working hours: 08:00 – 17:30, Saturday 08:00 – 13:00 and Sunday 09:00 – 13:00 (non-noisy works)

    For more information, consult the Enfield Council’s dedicated page: Road closures 

    This phase will lay the final pipework needed in Advent Way, including crossing the Pymmes Brook via a pipe bridge to connect to the already installed pipework. This completes the link between our energy centre on the EcoPark and the Meridian Water development. The remaining pipe installation and associated construction activities are planned to continue under approved lane closures, subject to weather and ground conditions.

    Traffic flow on Advent Way will be maintained under traffic light controls during the closure.

    Please note that between 12th February and 16th February 2024, whilst trial hole excavation is being carried out in Montagu Road, Advent Way will not have any Lane Closures.

    How may this work affect you?

    Access and Parking: Access will always be maintained for residents. In the event you might need assistance, please ask a member of our staff by contacting us with the numbers provided below.

    The work areas will be segregated by suitable fencing to ensure a safe working area for the work force and provide safe routes for the public at all times.

    Useful Contact details

    Emergency / Out of Hours Contacts:

    Project Manager:           Dan Pintea – 07478 833 389

    Contracts Manager:       Hakan Balcioglu – 07306 502 902

  • Upcoming works: Montagu Road

    Location/Area: Montagu Rd,

    Estimated start date: 12th February 2024

    Estimated end date:  16th February 2024

    Reason:  Trial Holes for Heat Network Extension

    Working hours:  08:00 – 17:30, Saturday 08:00 – 13:00 and Sunday 09:00 – 13:00 (non-noisy works)

    For more information, consult the Enfield Council’s dedicated page: Road closures 

    Investigative works on Montagu Rd which aims to assist with developing a suitable corridor for district heating pipes, between existing services.

    Due to critical locations of these trial holes, the safest method for works to be carried out is under directional road closure of Montagu Road from the junction with Conduit Ln to the junction with Town Road. The works will require a diversion route for the north heading lane of Montagu Rd.

    How may this work affect you?

    Access and Parking: Access will always be maintained for residents. In the event you might need assistance, please ask a member of our staff by contacting us with the numbers provided below.

    The work areas will be segregated by suitable fencing to ensure a safe working area for the work force and provide safe routes for the public at all times.

    Useful Contact details

    Emergency / Out of Hours Contacts:

    Site Manager:                 Andrew Heffernan – 07384 298 392

    Project Manager:           Dan Pintea – 07478 833 389

    Contracts Manager:       Hakan Balcioglu – 07306 502 902